§01 · Reference regression fixture · computed live by the engines
12 MW electrolysis pilot — full decision file
Every number below is produced at page load by the same engine chain the workspace runs: production → storage → transport → integration → environment → finance → social. Nothing is typed in by hand, and each figure carries its unit and the equation that produced it.
§02
Harmonised inputs
Base year 2026, commissioned 2028, EUR, 8 % real discount rate.
| Input | Value | Unit | Meaning |
|---|---|---|---|
| Technology | AEL | — | Alkaline electrolysis, register §3.4 cost curve |
| Capacity Q | 12 | MW | Electrical input rating of the electrolyser |
| Utilisation | 90 | % | Share of the 8 760 h year at rated load |
| Electricity price | 50 | €/MWh | Contracted PPA, real 2024 money |
| Grid carbon intensity | 25 | gCO₂e/kWh | Attributional factor for the PPA blend |
| Water price | 2.50 | €/m³ | Treated demineralised feed |
| Storage | 45 % CGH₂ 350 bar (24 h) + 15 % LH₂ (72 h) | % of output | Share of production routed through each store |
| Transport | 60 % truck 220 km + 40 % pipeline 40 km | % of output | Delivery legs, shares sum to 100 % |
| Sale price | 8.50 | €/kg | Gate price of hydrogen |
| Subsidy | 0.50 | €/kg | Production-linked support |
| Tax rate | 25 | % | Corporate income tax on profit after depreciation |
| Lifetime | 25 | yr | Economic life used for NPV and depreciation |
§03
Production
LCOH = (a × CAPEX + fixed OPEX + present value of stack replacements) ÷ annual kg, plus SEC × electricity price, plus water cost.
Annual output
1590.2 t H₂/yr
Mass leaving the electrolyser
Operating hours
7884 h/yr
8 760 × utilisation
Effective SEC
59.5 kWh/kg
Lifetime-average, degradation included
Installed CAPEX
€1026 €/kW
Register §3.4 power law at Q = 12 MW
Production LCOH
€4.07 €/kg
Levelised cost at the plant fence
Electricity share
€2.97 €/kg
SEC × price — usually the dominant term
§04
Investment — the money view
Capital is spent once, in year 0. Profit is delivered kilograms × price, minus cash operating cost and tax.
The identity used — and the mistake it avoids
Investment (€) = CAPEXproduction + CAPEXstorage + CAPEXtransport assets, escalated from the base year to commissioning at 2.0 %/yr.
Profit (€/yr) = delivered kg/yr × (price + subsidy) − cash OPEX (electricity, water, fixed O&M, storage compression/liquefaction energy, transport service) − tax on profit after straight-line depreciation.
Payback (yr) is where cumulative cash turns positive. It is never computed as CAPEX ÷ (price − LCOH): the levelised cost already contains an annuitised slice of that same CAPEX, so that formula charges the plant twice and produces impossible answers such as 49 years on a 25-year asset. Lifetime investment adds every operating year plus each stack replacement.
Initial investment
€50.48 M total CAPEX
Total CAPEX at commissioning
Cash OPEX
€5.33 M per year
Everything paid in cash each year
Revenue
€14.14 M per year
Delivered kg × (price + subsidy)
EBITDA
€8.81 M per year
Revenue − cash OPEX
Payback
7.1 yr
Cumulative cash crosses zero
Discounted payback
11.6 yr
Same, at 8 % discounting
NPV
€22.51 M @ 8 %
Present value of all cash flows
IRR
13.0 %
Discount rate at which NPV = 0
Lifetime investment
€192.43 M over 25 yr
CAPEX + replacements + all cash OPEX
Lifetime revenue
€353.56 M over 25 yr
All sales including subsidy
Lifetime net profit
€118.67 M over 25 yr
Revenue − lifetime investment − tax
Break-even price
€6.71 €/kg
Price at which NPV = 0
| Year | Revenue (€) | Cash OPEX (€) | Replacement CAPEX (€) | Tax (€) | Net cash (€) | Cumulative (€) |
|---|---|---|---|---|---|---|
| 0 | €0 | €0 | — | €0 | €-50.48 M | €-50.48 M |
| 1 | €14.14 M | €5.33 M | — | €1.70 M | €7.11 M | €-43.37 M |
| 2 | €14.14 M | €5.33 M | — | €1.70 M | €7.11 M | €-36.25 M |
| 3 | €14.14 M | €5.33 M | — | €1.70 M | €7.11 M | €-29.14 M |
| 10 | €14.14 M | €5.33 M | €4.36 M | €1.70 M | €2.76 M | €16.31 M |
| 20 | €14.14 M | €5.33 M | €4.36 M | €1.70 M | €2.76 M | €83.10 M |
| 25 | €14.14 M | €5.33 M | — | €1.70 M | €7.11 M | €118.67 M |
Cash-flow ledger (first years, every stack-replacement year, and the final year).
§05
Storage
LCOS = (a × CAPEX + OPEX) ÷ kg through the store + compression or liquefaction energy. Capacity is sized from the flow and the holding time.
Mass through storage
954.1 t/yr
Production × stored fraction
Installed capacity
3921 kg H₂
(flow ÷ 8 760) × holding hours
Portfolio LCOS
€0.45 €/kg stored
Weighted across the two stores
Energy penalty
0.146 €/kg
Compression 0.66 × ln(P₂/P₁), liquefaction 6.78 kWh/kg
Boil-off
2147 kg/yr
LH₂ only, 0.3 %/day over the hold
Handling loss
5963 kg/yr
Venting and residual heel
| Store | Share (%) | Hold (h) | CAPEX (€/kg cap.) | Energy (kWh/kg) | Boil-off (%/day) |
|---|---|---|---|---|---|
| CGH₂ 350 bar | 45 | 24 | €326 | 1.62 | 0.00 |
| Liquid H₂ | 15 | 72 | €900 | 6.78 | 0.30 |
Storage portfolio. Tank price follows p(P) = 0.346 × P + 286 €/kg (register §4.3).
§06
Transport & distribution
LCOT is the share-weighted tariff over the legs; the fleet or pipeline behind it is sized and priced as real capital.
Delivered volume
1571.4 t/yr
Production minus storage and transit losses
Daily delivery
4305 kg/day
Annual delivery ÷ 365
LCOT
€0.32 €/kg delivered
Weighted across all legs
Transport CAPEX
€33.21 M assets
Trailers, tractors and pipeline
Transit loss
10,750 kg/yr
Leakage and residual heel per km
Total chain loss
1.19 %
Storage + transport, of production
| Leg | Mode | Share (%) | Distance (km) | Mass (t/yr) | Tariff (€/kg) |
|---|---|---|---|---|---|
| Leg 1 | Truck · CGH₂ | 60 | 220 | 954.1 | €0.40 |
| Leg 2 | Pipeline | 40 | 40 | 636.1 | €0.20 |
§07
Environmental impacts — 16 indicators
Register §7. Curves are driven by the hydrogen-output capacity Q_H2,LHV, not the electrical rating.
Carbon intensity
1.76 kgCO₂e/kg H₂
Cradle-to-gate, delivered
RFNBO threshold
3.38 kgCO₂e/kg H₂
EU limit for renewable hydrogen
Headroom
1.62 kgCO₂e/kg H₂
Threshold minus actual — positive is compliant
Water intensity
10.0 L/kg H₂
Demineralised feed at the stack
Land footprint
0.0075 m²/(kg·yr)
Site area ÷ annual output
H₂ output capacity
6.72 MW (LHV)
Basis of every §7 curve
| ID | Indicator | Value | Unit | Equation / basis | Status |
|---|---|---|---|---|---|
| E01 | GHG emissions / GWP100 | 2233.800 | t CO₂-eq/y | M·SEC·CI electricity-driven screening (§7 E1) | calculated |
| E02 | Water consumption | 183,265 | m³/y | Lifecycle PV–PEM boundary 2.726e4·Q (§7 E2) | proxy |
| E03 | Transport GHG emissions | 318,050 | kg CO₂-eq/y | M_transported·(d/100)·EF (§7 E3) | calculated |
| E04 | Storage GHG emissions | 115,734 | kg CO₂-eq/y | M_cycled·e_storage·CF_elec (§7 E4) | calculated |
| E05 | Acidification | 8125.670 | kg SO₂-eq/y | 1.028e4·Q (§7 E5) · transferred k1=1.08, k2=0.11 (§9.4) | calculated |
| E06 | Particulate-matter formation | 3051.078 | kg PM₂.₅-eq/y | 3.860e3·Q (§7 E6) · transferred k1=1.08, k2=0.11 (§9.4) | calculated |
| E07 | Photochemical ozone formation | 3591.736 | kg NOx-eq/y | 4.544e3·Q, NOx-eq method (§7 E7) · transferred k1=1.08, k2=0.11 (§9.4) | calculated |
| E08 | Embodied CO₂ (stack + BoP) | 60.075 | t CO₂-eq/y | 8.936·Q reference portfolio allocation (§7 E8) | scenario |
| E09 | Metal and mineral depletion | 25,397 | kg Cu-eq/y | 3.213e4·Q (§7 E9) · transferred k1=1.08, k2=0.11 (§9.4) | calculated |
| E10a | Human toxicity | 0.109 | CTUh/y | 0.1376·Q (§7 E10) · transferred k1=1.08, k2=0.11 (§9.4) | proxy |
| E10b | Ecotoxicity | 1.65 × 10⁶ | CTUe/y | 2.089e6·Q (§7 E10) · transferred k1=1.08, k2=0.11 (§9.4) | proxy |
| E11a | Freshwater eutrophication | 675.980 | kg P-eq/y | 855.2·Q (§7 E11) · transferred k1=1.08, k2=0.11 (§9.4) | calculated |
| E11b | Marine eutrophication | 54.674 | kg N-eq/y | 69.17·Q (§7 E11) · transferred k1=1.08, k2=0.11 (§9.4) | calculated |
| E12 | Waste and end-of-life burden | 25,920 | kg/project | m_stack(n_rep+1)(1−r_recycle) (§7 E12) | calculated |
| E13 | Land / terrain footprint | 88.338 | ha | 13.14·Q, AWE + attributed PV generation (§7 E13) | scenario |
| E14 | Biodiversity loss | 0.000 | PDF·yr/y | 1.812e-9·Q (§7 E14) | proxy |
| E15 | Plant-boundary noise level | 56.807 | dB(A) | 90.6 + 7.5·log10 Q − 20·log10 r (§7 E15) | calculated |
| E16a | Noise-impacted area > 55 dB(A) | 0.048 | km² | 1.141e-2·Q^0.75 (§7 E16) | calculated |
| E16b | Persons highly annoyed | 0.285 | persons | 0.1107(Q−3.861)^0.8982 (§7 E16) | calculated |
| E16c | Noise-related DALYs | 0.006 | DALY/y | 0.002214(Q−3.861)^0.8982 (§7 E16) | calculated |
§08
Social impacts — 10 indicators
Register §8. Employment, exposure hours, local value added and consultation status.
Construction employment
192 FTE-years
Across the build period
Operational employment
4.2 FTE
Steady-state site staff
Local content
40 %
Share of spend with regional suppliers
Community index
68 score 0–100
Composite screening score
| ID | Indicator | Value | Unit | Equation / basis | Status |
|---|---|---|---|---|---|
| S01a | Employment — direct | 455.760 | job-years/project | 37.98·Q (§8 S1) | calculated |
| S01b | Employment — net | 859.622 | job-years/project | 71.6352·Q (§8 S1) | calculated |
| S02a | Work exposure — on-site risk hours | 11,504 | medium-risk h/project | 958.694·Q (§8 S2) | calculated |
| S02b | Work exposure — off-site risk hours | 277,013 | medium-risk h/project | 23 084.4·Q (§8 S2) | calculated |
| S02c | Expected fatalities | 0.003 | fatalities/project | r_h·H/10⁶ — needs a local sector fatality rate (§8 S2) | calculated |
| S03 | Community investment | 0.062 | M€/project | s_community·C(Q) — contract or policy coefficient required (§8 S3) | calculated |
| S04 | Energy security and access | 18,024 | persons-equivalent | 1502·Q energy-service proxy (§8 S4) | proxy |
| S05 | Education, skills and training | 34.380 | thousand training h/project | 2.865·Q (§8 S5) | proxy |
| S06 | Fair remuneration / labour compensation | 15.664 | GBP million/project | 1.30537·Q, regional IO boundary (§8 S6) | proxy |
| S07a | Land use exposure | 1.577 | km² | 0.1314·Q (§8 S7) | calculated |
| S07b | Land compensation | 11.66 × 10⁶ | €/project | A_land·c_ha — needs local land price (§8 S7) · k_L=0.95 vs WE (§9.1) | calculated |
| S08a | Noise annoyance — area > 55 dB(A) | 0.074 | km² | Shared physical chain with E15–E16 (§8 S8) | calculated |
| S08b | Noise annoyance — persons highly annoyed | 0.728 | persons | 0.1107(Q−3.861)^0.8982 (§8 S8) | calculated |
| S09 | Social and public acceptance | — | % | No capacity equation authorised. Benchmarks: nearby-hub support 55.23% (n=1682), positive general view 77.4% (§8 S9) | benchmark only |
| S10 | GDP contribution (GVA) | 38.462 | GBP million/project | 3.38·Q, regional IO boundary (§8 S10) · k_L=0.95 vs WE (§9.1) | proxy |
Open social risks
- Public consultation not yet completed
§09
Sensitivity and honest reading
Delivered LCOH
€5.14/kg
CalculatedSale price
€8.50/kg
ScenarioPreliminary gate
marginal
CalculatedFinal gate
favourable
CalculatedAt €5.14/kg delivered against a €8.50/kg gate price, this pilot clears the investment test with an NPV of €22.51 M and a payback of 7.1 years. H₂VALIS never rejects a project — it shows which assumption carries the answer, and the tornado above says electricity price and utilisation move it far more than CAPEX does.
§10
Units used on this page
| Symbol | Unit | Reads as |
|---|---|---|
| Q | MW | Electrical input capacity of the electrolyser |
| Q_H2,LHV | MW | Hydrogen output as lower-heating-value power |
| SEC | kWh/kg | Electricity consumed per kilogram of hydrogen |
| LCOH | €/kg | Levelised cost of hydrogen at the plant fence |
| LCOS | €/kg stored | Levelised cost of storage, per kilogram through the store |
| LCOT | €/kg delivered | Levelised cost of transport, per kilogram delivered |
| CAPEX | € | One-off capital spend, commissioning-year money |
| OPEX | €/yr | Recurring cash cost |
| EBITDA | €/yr | Revenue minus cash OPEX, before tax and capital |
| NPV | € | Present value of all cash flows at the discount rate |
| IRR | % | Discount rate at which NPV equals zero |
| GWP100 | kgCO₂e/kg H₂ | Global warming potential over 100 years |
| FTE | job-years | One person employed full time for one year |
| t | tonne | 1 000 kg |